CESC Commissions 147 MW Solar Project in Rajasthan's Bikaner

CESC Ltd has said 147 MW of its 150 MW solar power project at Bikaner in Rajasthan has begun commercial operations. The remaining 3 MW is expected to be commissioned by January 31, 2027, according to the company's regulatory filing.

Stockfame Editorial
Published: (43 min ago)
Last updated:
4 min read
WhatsApp

Key takeaways

  • 147 MW of CESC's 150 MW Bikaner solar project has started commercial operations.
  • The project is held through Deshraj Solar Energy Private Ltd, a step-down subsidiary of CESC.
  • A trial run certified by the Northern Regional Load Despatch Centre on November 19 cleared the way for operations.
  • The remaining 3 MW is expected to be commissioned by January 31, 2027.

CESC Ltd, the Kolkata-based power utility, has announced that 147 MW of its 150 MW solar power project in Rajasthan's Bikaner district has started commercial operations. The company described the development as a step forward in its renewable energy portfolio. It shared the update in a regulatory filing on Saturday, November 21.

What happened

According to the filing, the project is being developed by Deshraj Solar Energy Private Ltd, which CESC described as a step-down subsidiary. The plant is located at Karnisar Bhatiyan village in Bikaner district. It is connected to the Bikaner-III substation of Power Grid Corporation of India Ltd.

The 147 MW portion became operational after a successful trial run. The trial run was certified by the Northern Regional Load Despatch Centre of Grid Controller of India Ltd on November 19, the company said. The remaining 3 MW of the 150 MW capacity is expected to be commissioned by January 31, 2027.

In short, nearly the entire project is now live, and a small balance is still to be completed.

Key details at a glance

  • Project size: 150 MW solar power project
  • Capacity operational: 147 MW
  • Pending capacity: 3 MW, targeted by January 31, 2027
  • Location: Karnisar Bhatiyan village, Bikaner district, Rajasthan
  • Developer: Deshraj Solar Energy Private Ltd, a step-down subsidiary of CESC
  • Grid connection: Bikaner-III substation of Power Grid Corporation of India Ltd
  • Trial run certification: Northern Regional Load Despatch Centre, Grid Controller of India Ltd, November 19

Why it matters for investors

For investors who track CESC, the update shows progress on a renewable project that has moved from construction into the operating stage. A plant that has started commercial operations can begin supplying power under the terms of its arrangements. This is usually the point at which a project moves from being a capital expenditure item to being an operating asset.

The filing does not give the project cost, the tariff, the offtake arrangement or any estimate of revenue or profit from the plant. Investors should therefore avoid reading too much into the announcement beyond what the company has stated. Those details, if the company chooses to disclose them, would help in judging the project's financial contribution.

It is also worth noting that the capacity is being commissioned in two stages. Until the final 3 MW is completed, the project will run at slightly below its full 150 MW size. The company has given a timeline for the balance, and progress against that date is something market participants may follow.

Understanding the terms

What does "commercial operations" mean?

In the power sector, commercial operation generally means a plant has met the technical requirements to start supplying electricity regularly and is recognised as operational for the purposes of its contracts. Trial runs and testing usually come first. Here, the trial run was certified by the regional load despatch centre before the 147 MW was declared operational.

What is a step-down subsidiary?

A step-down subsidiary is a company owned by another subsidiary of the parent, rather than directly by the parent. Large groups often use such structures to house individual projects in separate companies. This can help in organising financing, approvals and accounting for each asset.

Role of the grid and load despatch centres

Utility-scale solar plants must be connected to the transmission network to deliver power. The Bikaner-III substation, run by Power Grid Corporation of India Ltd, is the connection point for this project. Load despatch centres coordinate the flow of electricity on the grid. Their certification of a trial run indicates that the plant has demonstrated it can operate while connected to the grid.

Background: Bikaner and solar power

Bikaner is in western Rajasthan, a state that is widely associated with large solar installations because of its high sunlight availability and large tracts of land. Several utility-scale solar projects have been set up in the state, and substations such as the one at Bikaner serve as evacuation points for such plants. The filing itself does not discuss these wider factors, but they help explain why solar developers look to this part of the country.

CESC is a Kolkata-based power company, and the filing describes the project as part of its renewable energy portfolio. The company did not provide figures in this filing on its overall renewable capacity, so this article does not estimate it.

What to watch next

  • Completion of the final 3 MW: The company expects this by January 31, 2027. Any update on the schedule would be disclosed through the exchanges.
  • Project economics: Details on tariff, offtake and cost, if shared in future disclosures or results commentary, would give a clearer picture of the project's impact.
  • Operating performance: Once a full quarter of operations is available, the company's financial results may show how the plant contributes to the numbers.
  • Further renewable additions: Investors may look for updates on other projects within the company's renewable portfolio.

This article is for information only and does not constitute investment advice. Readers should consult the company's official filings on the stock exchanges for the complete details.

Frequently asked questions

How much solar capacity has CESC commissioned in Bikaner?

CESC said 147 MW of its 150 MW solar power project in Bikaner, Rajasthan, has commenced commercial operations.

When will the remaining 3 MW be commissioned?

The company expects the remaining 3 MW to be commissioned by January 31, 2027.

Which company is developing the project?

The project is being developed by Deshraj Solar Energy Private Ltd, a step-down subsidiary of CESC.

Where is the project located and how is it connected to the grid?

It is at Karnisar Bhatiyan village in Bikaner district and is connected to the Bikaner-III substation of Power Grid Corporation of India Ltd.

Who certified the trial run?

The trial run was certified by the Northern Regional Load Despatch Centre of Grid Controller of India Ltd on November 19.

Make Stockfame a preferred source on GoogleSee our market stories first in Google Top Stories.
Get Stockfame stories first on GoogleFree · Done in 5 seconds · Undo anytime
KA
Reviewed byKritesh Abhishek

Kritesh Abhishek is an editor and reviewer at Stockfame with over 10 years of experience in financial news. An active investor for more than 13 years and the author of books on candlestick and chart-based trading, he reviews Stockfame's market and stock coverage, with a focus on what price moves, promoter actions and company news mean for retail investors.

Own a stock in this story? Check it for red flags in seconds. Open the checker →

This article is for information only and is not investment advice.